ABD Project Controls — Daily Dashboard

Olympic Dam · KAEFER · P6: 01 Jun 2026 · ITR: 10 Jul 2026 · Prepared: 10 Jul 2026
● Amber
Overall Status: AMBER — P6: 86.3% · ITR closure 57.2% (4,015/7,025) ↑ +451 closed since 27 May. CVC: 130/236 (55.1%). P6 finish 02 Nov 2026 · +105d vs CC target 20 Jul. 0 activities in negative floatfull schedule incl procurement · 182 construction-only · worst single activity: −26.1d.
Schedule: CC 24 Aug 2026 with subsystem 2730.113 and 2730.115 and punchlist complete to carry on beyond CC date. Critical path currently driven by QPEX pipe delivery.
Schedule Slip
+105d
P6 finish 02 Nov 2026 · vs CC target 20 Jul
📉
Negative Float
901 activities
with neg float · full schedule incl procurement
Worst activity: −26.1d
Days to CC
10d
Contractual CC 20 Jul 2026 · Forecast CC 24 Aug 2026
🚨
ITR Run Rate Risk
CC deadline 24 Aug (BHP working) · 67/day required · 10 Jul actual 9/day (last 24hrs)
Shortfall of 58/day. 3,010 remaining (as at 10 Jul). Breakdown: Civils 79.5% · E&I 64.4% · SMP 47.2%
67
Required/day
9
Current
45
Days to CC
ITR Closure by Process Area
Source: Completions Master Tracker 10 Jul 2026
Process AreaTargetClosedRemaining% Closed
ALL AREAS7,0254,0153,58857.2%
↑ +47 ITR scope vs 27 May (was 6,871) · +451 closed
2730 CPF Plant6,6523,2623,39049.0%
4000 Process End2666819825.6%
DisciplineTotalClosed% Closed
Civil46937379.5%
E&I3,1782,04664.4%
SMP3,3781,59647.2%
Discipline Closure %
Civil / E&I / SMP
Work Front Buckets
P6 data: 15 Jun 2026
BucketKAFICECATOtherTotal
A — In Progress1521233732344
B — Not Started1,0365671156602,378
C — Overdue00000
D — Stalled00000
* Other includes MTE (404 activities in B bucket) · Source: Construction Activities 01 Jun 2026
Work Front Visual
Stacked by company
Punchlist by Company & Category
Source: Punch Dashboard 17 Jun 2026 · Cat A = CVC blockers
CompanyCat ACat BCat CCat DTotal
KAEFER2833227414
ICE Engineering3139885235
CATCON0721480220
BHP-Copper06131736
Terra Mining05005
TOTAL1265771,1031131,919
Cat A: 5 open — CVC blockers across 2730-09 (3 items) and 2730-11 (2 items)
Punchlist Chart
By company & category
Commodity Tracking
P6: 15 Jun 2026 · Pipe Tracker: 8 Jul 2026 · Cable Tracker: 8 Jul 2026 · Report: 10 Jul 2026
87.1%
Piping — Poly Lines
KAF - POLY
Scope: 4443m
Last 7d (01 Jul–08 Jul): 543.9m
Subsystem Name % Total (m) Last 7d
2730.03 Overland Pipelines 100.0%
2446m 433.0m
2730.18 CPF Compressed Air System 100.0%
207m 80.0m
2730.19 CPF Potable Water System 100.0%
145m 30.9m
2730.20 CPF Plant Water System 18.0%
46m
2730.21 CPF Return Water System 0.0%
379m
4000.02 CPF Return Water HC Thickener 0.0%
170m
96.8%
Piping — Rest
KAF - REST
Scope: 8006m
Last 7d (01 Jul–08 Jul): 938.9m
Subsystem Name % Total (m) Last 7d
2730.03 Overland Pipelines 100.0%
2100m 433.0m
2730.10 CPF Filter Feed System 100.0%
297m 267.0m
2730.11 CPF Filtration System 100.0%
68m 6.0m
2730.14 CPF Mixing System 3.9%
76m
2730.15 CPF Transfer System 0.0%
25m
2730.16 Paste Pumps 0.0%
207m
2730.17 CPF Buildings 15.3%
976m 122.0m
2730.18 CPF Compressed Air System 100.0%
90m 80.0m
2730.19 CPF Potable Water System 100.0%
127m 30.9m
2730.20 CPF Plant Water System 18.0%
46m
2730.21 CPF Return Water System 0.0%
379m
4000.01 CCD Underflow Tailings 0.0%
954m
99.2%
Electrical
ICE - KAF - TERRA
Scope: 92904m
Subsystem Name % Total (m)
2730.08 CPF Structures 100.0%
3607m
2730.09 CPF Neutralisation & Filter Feed 99.8%
37880m
2730.10 CPF Filter Feed System 100.0%
4561m
2730.11 CPF Filtration System 100.0%
18496m
2730.12 CPF Filter Cake Transfer 95.8%
2476m
2730.13 CPF Lime Slaking System 94.1%
4099m
2730.14 CPF Mixing System 99.4%
2639m
2730.15 CPF Transfer System 95.5%
1495m
2730.16 Paste Plant 98.3%
3098m
2730.17 CPF Compressed Air System 100.0%
446m
2730.18 CPF Potable Water System 97.2%
5407m
2730.19 CPF Plant Water System 100.0%
3108m
2730.20 CPF Return Water System 100.0%
1035m
2730.21 CPF Sumps 100.0%
4257m
2730.22 CPF Ablution & Control Room 80.0%
300m
P6: 06 Jul 2026 · Master Tracker: 10 Jul 2026 · Pipe Tracker: 8 Jul 2026 · Cable Tracker: 8 Jul 2026 · Punchlist: 17 Jun 2026 · Report: 10 Jul 2026