ABD Project Controls — Daily Dashboard

Olympic Dam · KAEFER · P6: 27 Jul 2026 · ITR: 02 Aug 2026 · Prepared: 30 Jul 2026
● Amber
Overall Status: AMBER — P6: 90.0% · ITR closure 66.0% (4,650/7,050). CVC: 170/236 (72.0%). P6 finish 23 Nov 2026 · +126d vs CC target 20 Jul. 639 activities in negative floatfull schedule incl procurement.
Schedule: CC 24 Aug 2026 with subsystem 2730.113 and 2730.115 and punchlist complete to carry on beyond CC date. Critical path currently driven by QPEX pipe delivery.
Schedule Slip
+126d
P6 finish 23 Nov 2026 · vs CC target 20 Jul
📉
Negative Float
639 activities
with neg float · full schedule incl procurement
Days to CC
-10d
Contractual CC 20 Jul 2026 · Forecast CC 24 Aug 2026
🚨
ITR Run Rate Risk
CC deadline 24 Aug (BHP working) · 109/day required · 02 Aug actual 32/day (last 24hrs)
Shortfall of 77/day. 2,400 remaining (as at 02 Aug). Breakdown: Civils 83.0% · E&I 74.0% · SMP 55.8%
109
Required/day
32
Current
22
Days to CC
ITR Closure by Process Area
Source: Completions Master Tracker 02 Aug 2026
Process AreaTargetClosedRemaining% Closed
ALL AREAS7,0504,6502,40066.0%
ALL AREAS includes KAEFER and other delivery partners. Process Area rows below are KAEFER surface scope only.
2730 CPF Plant6,7714,6672,10468.9%
4000 Process End2828619630.5%
Remaining verified from Open ITR extracts (Civil/E&I/SMP, 02 Aug) — KAEFER surface scope only. Target from Master Tracker per-subsystem totals. Closed = Target − Remaining.
DisciplineTotalClosed% Closed
Civil47139183.0%
E&I3,2192,38374.0%
SMP3,3601,87655.8%
Discipline Closure %
Civil / E&I / SMP
Work Front Buckets
P6 data: 27 Jul 2026
BucketKAFICECATOtherTotal
A — In Progress1021183738295
B — Not Started4892081975791
C — Overdue00000
D — Stalled22115327115516
Work Front Visual
Stacked by company
Punchlist by Discipline & Category
Source: Punch Dashboard 17 Jun 2026 · Outstanding (open) punches · Cat A = CVC blockers
DisciplineCat ACat BCat CCat DTotal
Civils0752091285
E&I29212439257
SMP210026910381
Multi-Discipline17117618266
Vendor Packages/Skids0003737
TOTAL53387781051,226
Cat A: 5 open — CVC blockers: E&I (2), SMP (2), Multi-Discipline (1)
Punchlist Chart
By discipline & category (open punches)
Commodity Tracking
Piping scope figures: 01 Jun 2026 · Pipe Tracker: 30 Jul 2026 · Cable Tracker: 30 Jul 2026 · TPW Contractor: 1 Aug 2026 · Report: 30 Jul 2026
Note on 100% readings: Several subsystems show 100% because installed metres now exceed the scope figure.
101.0%
Piping — Poly Lines
KAF - POLY
Scope: 4443m
Last 7d (23 Jul–30 Jul): 168.4m
System Installed (m) Baseline Scope (m) % of Baseline Last 7d (m)
2730.03 3139.0m 2446.0m 128.3%
0.0m
2730.18 682.2m 207.0m 329.6%
150.4m
2730.19 199.6m 144.8m 137.9%
18.0m
2730.20 8.2m 45.6m 18.0%
2730.21 44.0m 378.9m 11.6%
0.0m
4000.02 0.0m 170.0m 0.0%
108.2%
Piping — Rest
KAF - REST
Scope: 8006m
Last 7d (23 Jul–30 Jul): 202.4m
System Installed (m) Baseline Scope (m) % of Baseline Last 7d (m)
2730.03 3139.0m 2099.7m 149.5%
0.0m
2730.10 328.5m 297.1m 110.6%
0.0m
2730.11 150.0m 67.5m 222.2%
16.0m
2730.13 248.0m 26.4m 939.4%
18.0m
2730.14 3.0m 76.5m 3.9%
2730.15 0.0m 25.0m 0.0%
2730.16 0.0m 206.7m 0.0%
2730.17 243.3m 975.8m 24.9%
0.0m
2730.18 625.2m 89.9m 695.4%
150.4m
2730.19 197.6m 126.9m 155.7%
18.0m
2730.20 8.2m 45.6m 18.0%
2730.21 0.0m 378.9m 0.0%
0.0m
4000.01 0.0m 953.7m 0.0%
99.4%
Electrical
ICE - KAF - TERRA
Scope: 92904m
Subsystem Name % Total (m)
2730.08 CPF Structures 100.0%
3607m
2730.09 CPF Neutralisation & Filter Feed 99.8%
37880m
2730.10 CPF Filter Feed System 100.0%
4561m
2730.11 CPF Filtration System 100.0%
18496m
2730.12 CPF Filter Cake Transfer 100.0%
2476m
2730.13 CPF Lime Slaking System 94.6%
4099m
2730.14 CPF Mixing System 100.0%
2639m
2730.15 CPF Transfer System 97.6%
1495m
2730.16 Paste Plant 98.3%
3098m
2730.17 CPF Compressed Air System 100.0%
446m
2730.18 CPF Potable Water System 97.5%
5407m
2730.19 CPF Plant Water System 100.0%
3108m
2730.20 CPF Return Water System 100.0%
1035m
2730.21 CPF Sumps 100.0%
4257m
2730.22 CPF Ablution & Control Room 100.0%
300m
P6: 27 Jul 2026 · Master Tracker: 02 Aug 2026 · Pipe Tracker: 30 Jul 2026 · Cable Tracker: 30 Jul 2026 · Punchlist: 17 Jun 2026 · Report: 30 Jul 2026