ABD Project Controls — Daily Dashboard

Olympic Dam · KAEFER · P6: 20 Jul 2026 · ITR: 15 Jul 2026 · Prepared: 23 Jul 2026
● Amber
Overall Status: AMBER — P6: 93.5% · ITR closure 59.0% (4,142/7,018) ↑ +451 closed since 27 May. CVC: 142/237 (59.9%). P6 finish 13 Sep 2026 · +55d vs CC target 20 Jul. 0 activities in negative floatfull schedule incl procurement.
Schedule: CC 24 Aug 2026 with subsystem 2730.113 and 2730.115 and punchlist complete to carry on beyond CC date. Critical path currently driven by QPEX pipe delivery.
Schedule Slip
+55d
P6 finish 13 Sep 2026 · vs CC target 20 Jul
📉
Negative Float
0 activities
with neg float · full schedule incl procurement
Days to CC
-3d
Contractual CC 20 Jul 2026 · Forecast CC 24 Aug 2026
🚨
ITR Run Rate Risk
CC deadline 24 Aug (BHP working) · 90/day required · 11 Jul actual 55/day (last 24hrs, no newer PDF)
Shortfall of 35/day. 2,876 remaining (as at 15 Jul, Master Tracker). Breakdown: Civils 79.5% · E&I 65.3% · SMP 48.0% (as at 11 Jul, last PDF)
90
Required/day
55
Current
32
Days to CC
ITR Closure by Process Area
Source: Completions Master Tracker 15 Jul 2026
Process AreaTargetClosedRemaining% Closed
ALL AREAS7,0184,1423,58859.0%
2730 CPF Plant6,7364,0662,67060.4%
4000 Process End2827620627.0%
DisciplineTotalClosed% Closed
Civil46937379.5%
E&I3,1722,07165.3%
SMP3,3701,61848.0%
Discipline Closure %
Civil / E&I / SMP
Work Front Buckets
P6 data: 20 Jul 2026
BucketKAFICECATOtherTotal
A — In Progress1491624352406
B — Not Started537345522041,138
C — Overdue00000
D — Stalled00000
Work Front Visual
Stacked by company
Punchlist by Company & Category
Source: Punch Dashboard 17 Jun 2026 · Cat A = CVC blockers
CompanyCat ACat BCat CCat DTotal
KAEFER2833227414
ICE Engineering3139885235
CATCON0721480220
BHP-Copper06131736
Terra Mining05005
TOTAL1265771,1031131,919
Cat A: 5 open — CVC blockers across 2730-09 (3 items) and 2730-11 (2 items)
Punchlist Chart
By company & category
Commodity Tracking
Piping scope figures: 01 Jun 2026 · Pipe Tracker: 23 Jul 2026 · Cable Tracker: 23 Jul 2026 · Report: 23 Jul 2026
Note on 100% readings: Several subsystems show 100% because installed metres now exceed the scope figure.
100.6%
Piping — Poly Lines
KAF - POLY
Scope: 4443m
Last 7d (16 Jul–23 Jul): 662.0m
Subsystem Name % Total (m) Last 7d
2730.03 Overland Pipelines 100.0%
2446m 600.0m
2730.18 CPF Compressed Air System 100.0%
207m 62.0m
2730.19 CPF Potable Water System 100.0%
145m 0.0m
2730.20 CPF Plant Water System 18.0%
46m
2730.21 CPF Return Water System 0.0%
379m
4000.02 CPF Return Water HC Thickener 0.0%
170m
108.0%
Piping — Rest
KAF - REST
Scope: 8006m
Last 7d (16 Jul–23 Jul): 743.0m
Subsystem Name % Total (m) Last 7d
2730.03 Overland Pipelines 100.0%
2100m 600.0m
2730.10 CPF Filter Feed System 100.0%
297m 0.0m
2730.11 CPF Filtration System 100.0%
68m 7.0m
2730.14 CPF Mixing System 3.9%
76m
2730.15 CPF Transfer System 0.0%
25m
2730.16 Paste Pumps 0.0%
207m
2730.17 CPF Buildings 24.9%
976m 74.0m
2730.18 CPF Compressed Air System 100.0%
90m 62.0m
2730.19 CPF Potable Water System 100.0%
127m 0.0m
2730.20 CPF Plant Water System 18.0%
46m
2730.21 CPF Return Water System 0.0%
379m
4000.01 CCD Underflow Tailings 0.0%
954m
99.4%
Electrical
ICE - KAF - TERRA
Scope: 92904m
Subsystem Name % Total (m)
2730.08 CPF Structures 100.0%
3607m
2730.09 CPF Neutralisation & Filter Feed 99.8%
37880m
2730.10 CPF Filter Feed System 100.0%
4561m
2730.11 CPF Filtration System 100.0%
18496m
2730.12 CPF Filter Cake Transfer 100.0%
2476m
2730.13 CPF Lime Slaking System 94.3%
4099m
2730.14 CPF Mixing System 100.0%
2639m
2730.15 CPF Transfer System 96.1%
1495m
2730.16 Paste Plant 98.3%
3098m
2730.17 CPF Compressed Air System 100.0%
446m
2730.18 CPF Potable Water System 97.5%
5407m
2730.19 CPF Plant Water System 100.0%
3108m
2730.20 CPF Return Water System 100.0%
1035m
2730.21 CPF Sumps 100.0%
4257m
2730.22 CPF Ablution & Control Room 100.0%
300m
P6: 20 Jul 2026 · Master Tracker: 15 Jul 2026 · Pipe Tracker: 23 Jul 2026 · Cable Tracker: 23 Jul 2026 · Punchlist: 17 Jun 2026 · Report: 23 Jul 2026