ABD Project Controls — Daily Dashboard

Olympic Dam · KAEFER · P6: 24 Aug 2026 · ITR: 09 Aug 2026 · Prepared: 27 Aug 2026
● Amber
Overall Status: AMBER — P6: 97.1% · ITR closure 70.7% (4,999/7,069). CVC: 177/236 (75.0%). P6 finish 20 Sep 2026 · +62d vs CC target 20 Jul. 542 activities in negative floatfull schedule incl procurement.
Schedule: CC 24 Aug 2026 with subsystem 2730.11 and 2730.15 and punchlist complete to carry on beyond CC date. Critical path currently driven by QPEX pipe delivery.
Schedule Slip
+62d
P6 finish 20 Sep 2026 · vs CC target 20 Jul
📉
Negative Float
542 activities
with neg float · full schedule incl procurement
Days to CC
-38d
Contractual CC 20 Jul 2026 · Forecast CC 24 Aug 2026
🚨
ITR Run Rate Risk
CC deadline 24 Aug (BHP working) · 138/day required · 09 Aug actual 20/day (last 24hrs)
Shortfall of 118/day. 2,070 remaining (as at 09 Aug). Breakdown: Civils 83.7% · E&I 79.0% · SMP 60.8%
138
Required/day
20
Current
15
Days to CC
ITR Closure by Process Area
Source: Completions Master Tracker 09 Aug 2026
Process AreaTargetClosedRemaining% Closed
ALL AREAS7,0694,9992,07070.7%
ALL AREAS includes KAEFER and other delivery partners. Process Area rows below are KAEFER surface scope only.
2730 CPF Plant6,7714,6672,10468.9%
4000 Process End2828619630.5%
Process Area — Remaining verified from a dedicated open-ITR-by-area export (last pulled 02 Aug). Target from Master Tracker per-subsystem totals. Closed = Target − Remaining.
Source: Completions Master Tracker 09 Aug 2026
DisciplineTotalClosed% Closed
Civil47239583.7%
E&I3,2482,56579.0%
SMP3,3492,03760.8%
Discipline Closure %
Civil / E&I / SMP
Work Front Buckets
P6 data: 24 Aug 2026
BucketKAFICECATOtherTotal
A — In Progress1141153843310
B — Not Started153891229283
C — Overdue00000
D — Stalled1911271561394
Work Front Visual
Stacked by company
Punchlist by Discipline & Category
Source: ABD Punchlist Tracker R1, 08 Aug 2026 · Open punches · Cat A = CVC blockers
DisciplineCat ACat BCat CCat DTotal
Civils0232671291
E&I11122315250
SMP113756618722
Multi-Discipline1491999258
Vendor Packages/Skids00022
TOTAL32201,255451,523
Cat A: 3 open — CVC blockers: E&I (1, PL-005757 generator fire alarm wiring), SMP (1, PL-008470 purge grease lines), Multi-Discipline (1, PL-007446 NCR non-compliant fire system)
Punchlist Chart
By discipline & category (open punches)
Commodity Tracking
Piping scope figures: 01 Jun 2026 (revised 03 Aug, 10 Aug, 17 Aug, 24 Aug 2026 for select subsystems, see ABD Schedule / 2WLA Reports) · Pipe Tracker: 20 Aug 2026 · Cable Tracker: 10 Aug 2026 · TPW Contractor: 11 Aug 2026 · Report: 27 Aug 2026
Note on 100% readings: Several subsystems show 100% because installed metres now exceed the scope figure.
99.9%
Piping — Poly Lines
KAF - POLY
Scope: 4,561.8m
Last 7d (14 Aug–20 Aug): 147.5m
System Installed (m) Baseline Scope (m) % of Baseline Last 7d (m)
2730.03 3150.0m 2446.0m 128.8%
0.0m
2730.18 878.2m 207.0m 424.3%
115.0m
2730.19 256.1m 266.1m 96.2%
32.5m
2730.20 8.2m 45.6m 18.0%
2730.21 44.0m 378.9m 11.6%
0.0m
2730.09 0.0m 7.0m 0.0%
2730.13 0.0m 7.0m 0.0%
2730.23 0.0m 16.0m 0.0%
4000.02 0.0m 170.0m 0.0%
95.1%
Piping — Rest
KAF - REST
Scope: 9,890.6m
Last 7d (14 Aug–20 Aug): 213.5m
System Installed (m) Baseline Scope (m) % of Baseline Last 7d (m)
2730.03 3139.0m 2099.7m 149.5%
0.0m
2730.09 0.0m 23.0m 0.0%
2730.10 355.5m 297.1m 119.7%
27.0m
2730.11 150.0m 67.5m 222.2%
0.0m
2730.13 264.0m 307.0m 86.0%
5.0m
2730.14 3.0m 76.5m 3.9%
2730.15 0.0m 136.0m 0.0%
2730.16 0.0m 206.7m 0.0%
2730.17 292.3m 975.8m 30.0%
34.0m
2730.18 808.2m 686.2m 117.8%
115.0m
2730.19 254.1m 257.1m 98.8%
32.5m
2730.20 8.2m 95.2m 8.6%
2730.21 0.0m 378.9m 0.0%
0.0m
4000.01 0.0m 953.7m 0.0%
4401.01 0.0m 907.0m 0.0%
93.5%
Electrical
ICE - KAF - TERRA
Scope: 94520m
Subsystem Name % Total (m)
2730.08 CPF Structures 98.0%
2703m
2730.09 CPF Neutralisation & Filter Feed 93.6%
37802m
2730.10 CPF Filter Feed System 96.1%
4745m
2730.11 CPF Filtration System 99.9%
19383m
2730.12 CPF Filter Cake Transfer 99.0%
2577m
2730.13 CPF Lime Slaking System 80.4%
4449m
2730.14 CPF Mixing System 88.9%
3237m
2730.15 CPF Transfer System 93.4%
1725m
2730.16 Paste Plant 91.0%
3199m
2730.17 CPF Compressed Air System 99.6%
446m
2730.18 CPF Potable Water System 74.5%
5407m
2730.19 CPF Plant Water System 91.4%
3108m
2730.20 CPF Return Water System 100.0%
1035m
2730.21 CPF Sumps 97.3%
4404m
2730.22 CPF Ablution & Control Room 100.0%
300m
P6: 24 Aug 2026 · Master Tracker: 09 Aug 2026 · Pipe Tracker: 20 Aug 2026 · Cable Tracker: 10 Aug 2026 · Punchlist: 08 Aug 2026 · Report: 27 Aug 2026